UP-DATE PROGRESS SITES – 2

Up-dated 15 November 2011

 

14. Banyuresmi – Garut.

CME FINISH & PLN CONNECTED.

Invoicing.

15. Istana Mekar Wangi – Bandung.

CME FINISH.

Invoicing. Finished***

16. Pamendong – Tarogong, Garut. (TO)

PLN CONNECTED.

17. Muncang Agung – Malangbong, Garut (TO).

PLN Connected.

18. Dusun Tengah – Indramayu.

PLN Connected.

19. Jembatan Senen – Indramayu.

PLN Connected.

20. Kiajaran Kulon – Indramayu.

Proposed power voltage not available.

PLN Connected at 10,6 KVA.

21. Cugenang – Bayabang, Cianjur.

– 2 Electric Poles extension installed.

– PLN Connected.

22. Karang Tengah – Cianjur.

– 2 Electric Pole Extension installed.

– PLN Connected.

23. Lanud Sulaeman – Pesantren, Kopo. (BKM)

PLN Connected at 5,5 KVA within 4 days after Reg. payment.

Invoicing..

24. Pasawahan – Purwakarta.

PLN connected at 5,5 KVA.

Invoicing….

25. Laksanamekar – Padalarang.

PLN Connected at 6,6KVA.

Invoicing.

26. Sriwijaya – Bandung.

PLN connection 5,5 KVA.

Waiting for Purchasing Order.

27. Ujung Berung – Bandung.

PLN Connected at 6,6 KVA within 4 days since reg. payment.

Invoicing…

28. Sinyar – Kamulyan, Tasikmalaya.

PLN Connected at 5,5 KVA within 4 days since reg. payment.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s