Last Update : 15 November 2011
Up-date tanggal 08 Agustus 20111.
1. Site Adi Kusumah - Bale Endah
CME Finish, PLN Connected, Pra-ATP ada catatan pending item minor, Pending item repaired.
Ready for ATP. Closing
On-air.
-
2. Site H.Haris - Baros
CME Finish, Pending item sudah diperbaiki.
Siap untuk ATP. Closing.
On-Air
-
3. Site Hasan ll - Ciparay
Progress 80%, community blocking issue.
Sisa pekerjaan : Instal sebagian tray, instal panel, connect PLN.
-
4. Site Cugenang Gedeh
CME Finish, PLN Connected.
Ada pending item.
Finished***
-
5. Site Cisaranten Wetan.
CME Finish, ada pending item.
Pending item repaired. Invoicing.
Finished***
-
6. Site Ciputat Tegalluar
Selesai pondasi, siap dismantle pagar dan restorasi kembali, siap instal material pabrikasi.
-
7. Site Giri Indah
CME Finish, siap connect PLN (menunggu PO).
Repaired.
Finished***
-
8. Site Tegal Kawung - Cipageran
CME Finish, siap connect PLN (menunggu PO).
Ada pending item.
Pending item repaired. Invoicing.
-
9. Site Jebrod - Cilaku
Selesai pondasi, material pabrikasi siap, menunggu panel dari pihak ke-3, siap connect PLN.
Finished***
-
10. Site Pataruman - Kawung Luwuk
Selesai pondasi, material pabrikasi siap, menunggu panel dari pihak ke-3, siap connect PLN.
08 Agustus 2011 CME Finish. Siap connect PLN.
Finished***
-
11. Site Cihideung - Yudanegara
Finished, siap ATP.
-
12. Site ITT-Cinunuk
Sudah di-install. Ada keluhan mengenai material, sedang dilakukan proses uji tarik.
Finished***
-
13. Site Ahmad Yani
Sudah di install namun ada revisi (penambahan item barang).
Sudah dipabrikasi dan dalam proses galvanis.
Finished***
By,
Fin.