Site Laksanamekar Padalarang

Date : 19 Mei 2011

Data : Estimasi CME Progress 85 %. Menunggu Panel untuk koneksi.

Foto doc ; n/a yet.

Power Status :

  • Aplikasi PLN telah kami terima dan diregistrasi by manual (via insider).
  • Menunggu SIP dan PJBTL (manager UPJ cuti).
  • est. koneksi 6-9 hari kerja.
By,
FIN