Site Banyuresmi Garut

PLN Connected tgl. 15 Juli 2011

BP PLN lunas tgl. 04 Juli 2011

Progress pekerjaan kami sudah CME Finish. Menunggu koneksi Daya Listrik PLN.

Foto dokumentasi masih berada pada memory camera di lapangan.

Canopi, Tray, Pole PLN, Panel sudah terinstall

Status Power : Aplikasi PLN belum kami terima.

By,

CV. FIN